Metal Box Limited v. Mr.Lalit Kumar Nagpal
503-CAF77-18-DELAY.DOC SSK
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
CIVIL APPELLATE JURISDICTION CIVIL APPLICATION NO. 77 OF 2018 IN FIRST APPEAL NO. 611 OF 2013 Metal Box Limited ...Applicant
Versus
Lalit Kumar Nagpal
...Respondent
Mr. Chirag Mody, a/w Mr. Rushabh Parekh, i/b DSK Legal, for the Applicant.
Mr. M. Sanghai, i/by Ishwarprasad Bagaria, for the Respondent.
CORAM: Smt. Anuja Prabhudessai, J DATE : 16th April, 2018.
PC:- 1.
Not on board. Mentioned. Taken on production board. 2.
By this application the Applicant sought to condone the delay in filing restoration application to restore the appeal which was dismissed for non-compliance of the conditions in order dated 10th February, 2015. The learned Counsel for the Applicant submits that he will comply with the order dated 10th February, 2015 within two weeks from today. Statement accepted. Having heard the learned Counsel for the Applicant 1/2
503-CAF77-18-DELAY.DOC and the learned Counsel for the Respondent and having seen the averments made in paragraphs 6, 7, 8 and 9 of the application, which in my considered view, constitute sufficient grounds, the delay is condoned subject to payment of costs of Rs.10,000/-. Appeal is ordered to be restored. All orders passed in interim application stand restored. The Civil Application is disposed of.
[Smt. Anuja Prabhudessai, J.] 2/2