Shamshad Begum Babu Shaikh v. Municipal Corporation Of Greater Mumbai
6-caf-896-2014.doc
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
CIVIL APPELLATE JURISDICTION CIVIL APPLICATION NO.896 OF 2014 IN FIRST APPEAL (ST) NO.13406 OF 2012 Shamshad Begum Babu Shaikh ... Appellant vs.
Municipal Corporation of Greater Bombay ... Respondent Mr. A.A. Desai, for the Appellant.
Mr. A.R. Bhoair, for the Respondent.
CORAM:
MRS.MRIDULA BHATKAR, J.
DATE:
AUGUST 21, 2015 P.C.:
.
The application is moved for restoration of First Appeal which was dismissed for non compliance of the order dated 27th September, 2013 in Civil Application No. 3609 of 2013 for restoration.
2.
The learned counsel for the Appellant submits that the order was not complied Vishal 1 / 2
6-caf-896-2014.doc inadvertently. However, now the Appellant is ready to remove all the office objections and he has good case on merit.
3.
The learned counsel for the RespondentCorporation opposed the application. 4.
In view of the submission made by the learned counsel for the Applicant/Appellant, the order dated 19th December, 2013 is recalled and the proceeding are restored. The order of this Court dated 27th September, 2013 is to be complied within six weeks and if not complied, the matter will be dismissed without further reference to the Court. (MRS.MRIDULA BHATKAR, J.) 2 / 2