← Library
Bombay High CourtCAF/335/2016allowed

The Oriental Insurance Co. Ltd. Through Mumbai Third Party Hub v. Mr. Marcus E. Bhonsale And ORS.

2016-08-10Hon'Ble Shri Justice R.M. Savant.2 pages

(26) caf-335.16

IN THE HIGH COURT OF JUDICATURE AT BOMBAY

CIVIL APPELLATE JURISDICTION CIVIL APPLICATION NO.335 OF 2016 IN FIRST APPEAL STAMP NO.2167 OF 2015 The Oriental Insurance Co. Ltd.

: Applicant.

Versus

Marcus E Bhonsale and ors.

: Respondents.

Mr. D S Joshi for the Applicant.

Mrs. Varsha Chawan for the Respondent Nos.1 to 3 CORAM :

R. M. SAVANT, J.

DATE :

10th August 2016 P.C.

The above Civil Application has been filed for condonation of delay of 122 days in filing the above First Appeal. The reasons therefor a re mentioned in the above Civil Application.

The learned counsel appearing on behalf of the Respondent Nos.1 to 3 - Claimants Mrs. Varsha Chawan opposes the Application but ultimately leaves it to this Court.

Having regard to the grounds of challenge the presence of the Respondent No.4 is not necessary according to the learned counsel for the Applicant.

lgc

(26) caf-335.16 Hence having regard to the reasons mentioned in the above Civil Application, case for condonation of delay of 122 days in filing the above First Appeal is made out. The above Civil Application is accordingly allowed. Resultantly the delay of 122 days in the filing the above First Appeal stands condoned. The above Civil Application is accordingly disposed of. [R.M.SAVANT, J] lgc