State Of Maharashtra Through The Dept. Labour v. D N Wind Systems India Pvt. Ltd.
40-ia-19101-2022 in wp-6133-2021.doc Pallavi
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
CIVIL APPELLATE JURISDICTION by PALLAVI MAHENDRA WARGAONKAR Date:
2022.11.09 20:36:51 +0530 PALLAVI MAHENDRA WARGAONKAR INTERIM APPLICATION NO.19101 OF 2022 IN WRIT PETITION NO.6133 OF 2021 The State of Maharashtra ...Applicant In the matter between D.N. Wind Systems India Pvt. Ltd.
...Petitioner
Vs.
State of Maharashtra and Ors.
...Respondents
-------------- Smt. V.S. Nimbalkar, AGP for Applicant/State. Ms. Shraddha Pawar i/by Nitesh Patil, for Respondents. --------------- CORAM: MADHAV J. JAMDAR, J.
DATE:
NOVEMBER 9, 2022 P.C.:
1.
The relief sought in the Interim Application is to grant extension of time for a period of four weeks to conclude the hearing and pass final order on the application dated 25th February 2021 filed under section 25-O(1) of the Industrial Disputes Act, 1947.
2.
This Court by order dated 15th December 2021 passed in Writ Petition No.6133 of 2021 requested Hon'ble Minister to decide said
40-ia-19101-2022 in wp-6133-2021.doc proceedings within a period of six weeks. The present Interim Application has been filed on 25th January 2022. However, the final order, after giving hearing has been passed on 16th March 2022. Therefore, no orders are required to be passed in this Interim Application. Interim Application is disposed of. (MADHAV J. JAMDAR, J.)