IN THE HIGH COURT OF JUDICATURE AT BOMBAY

CIVIL APPELLATE JURISDICTION WRIT PETITION NO. 1293 OF 2013 Jijaram Dinkar Sankpal ...

Petitioner V/s.

Shri Bhima P. Kale & ors.

...

Respondents Mr. S.V. Marne for the petitioners.

Mr. Niranjan P. Shimpi for respondent no.1.

Mr. C.P. Yadav, AGP for respondent no.2.

CORAM :

NARESH H. PATIL AND A.S. GADKARI, JJ.

12th January, 2015.

P.C.

Heard learned Counsel for the parties.

2.

Petitioner was posted as Sectional Engineer, Kondhapuri Irrigation Section on 13th July, 2012. It is submitted that respondent wanted transfer at petitioner's place. It is submitted that due to pendency of the petition before the Tribunal and interim order granted by this Court, the petitioner is continuing in the said post for last two and half years.

3.

We have heard the submissions of learned Counsel for the petitioner and respondent no.1. Due to subsequent developments and efflux of time, we find it appropriate not to deal with the issues raised by the petitioner on merits. The

2/2 wp1293.13.sxw petitioner would complete three years term at Kondhapuri Irrigation Section within six months time. We observe that after the petitioner completes six months period of service at Kondhapuri Section, the respondents nos. 2 and 3 shall pass appropriate orders in accordance with transfer policy. 4.

With aforesaid observations, Writ Petition is disposed of. (A.S. GADKARI, J.) (NARESH H. PATIL, J.) L.S. Panjwani, P.S.