IN THE HIGH COURT OF JUDICATURE AT BOMBAY

CIVIL APPELLATE JURISDICTION BASAVRAJ GURAPPA PATIL Date: 2023.03.16 11:35:43 +0530 WRIT PETITION NO. 2789 OF 2023 WITH INTERIM APPLICATION (ST) NO.6795 OF 2023 WITH INTERIM APPLICATION (ST) NO.6793 OF 2023 IN WRIT PETITION NO. 2789 OF 2023 KRG Enterprises ..... Petitioner Vs.

The State of Maharashtra & Ors.

..... Respondents M/s. Sarvadnya Shree Infra Pvt. Ltd.

..... Applicant M/s. a. P. Ghuge Construction Co.

..... Applicant Mr. Swapnil K. Walve for the Petitioner Ms. R. A. Salunkhe, AGP for the State Mr. Parag Vyas a/w. Mr. Ashutosh Mishra, Ms. Karuna Yadav, Satyaprakash Mishra for Respondent No.4 Ms. Ushajee Peri with Krupali H. Rajani i/b. Lexicorp Partners for Respondent Nos.2 and 3 Mr. Swanand Joshi, Mr. H. Rokade and Mr. Devidas Raut on behalf of MAHAGENCO.

CORAM:

S.V.GANGAPURWALA, ACJ & SANDEEP V. MARNE, J.

DATED :

MARCH 15, 2023 P.C.

1.

The learned Counsel for the Petitioner submits that after the Writ Petition is filed, Respondent No.2 and 3 have issued notice to those two persons to stop the work of ash excavation/lifting. Basavraj 1/2

4.2789.23-wp.docx 2.

The learned Counsel for Respondent Nos.2 and 3 submits that the contract with one had come to an end on 13th March 2023. So far as another person is concerned, he has been directed to stop the work, in view of the finalization of the e-auction process scheduled to be held on 16th March 2023.

3.

In view of the same, the purpose of the Writ Petition stands served. The Writ Petition is disposed of. No costs. 4.

The Interim Applications also stand disposed of. (SANDEEP V. MARNE, J) (ACTING CHIEF JUSTICE) Basavraj 2/2