← Library
Bombay High CourtWP/3618/2018allowed to be withdrawn

M/S. S.K. Construction And Co. Through Its Partner And ORS. v. The District Magistrate, Pune And ORS.

2018-04-02Hon'Ble Shri Justice A.A. Sayed,Hon'Ble Shri Justice Ravindra V. Ghuge1 pages

27.WP.3618.18.doc

IN THE HIGH COURT OF JUDICATURE AT BOMBAY

CIVIL APPELLATE JURISDICTION WRIT PETITION NO. 3618 OF 2018 M/s. S.K. Construction and Co.

through its Partners & Ors.

... Petitioners V/s.

The District Magistrate, Pune & Ors.

... Respondents Mr. Vivek V. Salunke for the Petitioners.

Ms. Jyoti P. Jadhav, A.G.P. for the State.

CORAM :

A.A. SAYED AND RAVINDRA V. GHUGE, JJ.

DATE :

2ND APRIL, 2018.

P.C. :

On the request of learned Counsel for the Petitioners, the Petition is allowed to be withdrawn with liberty to take recourse to appropriate remedy available to the Petitioners in law. (RAVINDRA V. GHUGE, J.) (A.A. SAYED, J.) Waghmare 1/1