← Library
Bombay High CourtWP/5458/2023disposed off

Shree Pashupati Construction v. The State Of Maharashtra And ORS

2023-08-07Hon'Ble Shri Justice G. S. Kulkarni,Hon'Ble Shri Justice Jitendra Shantilal Jain1 pages

TAUSEEF LAIQUEE FAROOQUI Tauseef 10-WP.5458.2023.doc IN THE HIGH COURT OF JUDICATURE AT BOMBAY TAUSEEF LAIQUEE FAROOQUI Date: 2023.08.07 20:09:46 +0530 CIVIL APPELLATE JURISDICTION WRIT PETITION NO.5458 OF 2023 Shree Pashupati Construction

...Petitioner

Versus

The State of Maharashtra & Ors.

...Respondents

******** Mr. Rahul Thakar, i/by Mr. C. B. Thakar for the Petitioner. Ms. Shruti D. Vyas, 'B' Panel Counsel for the Respondent (State). ******** CORAM : G. S. KULKARNI, JITENDRA JAIN, J.J.

DATE : 7th AUGUST, 2023.

P.C.

.

After this petition was heard for some time, Mr. Thakar, learned counsel for the Petitioner fairly states that he seeks leave to withdraw the present petition with liberty to the Petitioner to approach the Appellate Authority. Allowed to be withdrawn with liberty as prayed for.

2.

Disposed of. No costs.

3.

All contentions of the parties are expressly kept open. 4.

In the event, the Appeal is fled within 2 weeks from today, the same be decided on merits, without raising an objection as to limitation as the Petitioner was bonafde pursing this petition.

[JITENDRA JAIN, J.] [G. S. KULKARNI, J.]