IN THE HIGH COURT OF JUDICATURE AT BOMBAY
SALGAONKAR M M Date: 2022.04.20 17:41:31 +0530 SALGAONKAR M M CIVIL APPELLATE JURISDICTION INTERIM APPLICATION NO.2479 OF 2022 IN APPEAL FROM ORDER (ST) NO.6993 OF 2022 Ishwari Gulabrai Dasani & Anr.
..
Applicants
Versus
Dhanashree Constructions through it's partners Ramesh Kesarimal Sonigra & Ors.
..
Respondents ...
Mr.Sandeep Sharma i/b Mr.Sanjeev Kumar Rapolu for the Applicants.
...
CORAM: BHARATI DANGRE, J.
DATED : 18th APRIL, 2022 P.C:- 1.
At the outset, the learned counsel for the applicants/appellants states that he has fled an interim application for stay, but the same is fled as part of Appeal from Order and, therefore, is not registered separately. He, therefore, seeks permission to segregate the same and get it numbered.
Liberty as prayed for, is granted.
M.M.Salgaonkar
2/2 26 IA-2479-22.doc INTERIM APPLICATION NO.2479 OF 2022 2.
Heard the learned counsel for the applicants and perused the application, which seeks condonation of delay of 11 days in instituting the appeal.
3.
On perusal of the application, it can be seen that the impugned judgment is delivered on 21/01/2022 and the certifed copy is received on 24/01/2022. The applicants explained that some time was consumed in seeking legal advise and the appeal came to be instituted on 04/03/2022. This has resulted in delay of 11 days. On hearing the learned counsel for the applicant, I am convinced to condone the delay. The application is allowed in terms of prayer clause (a). APPEAL FROM ORDER (ST) NO.6993 OF 2022 4.
Issue notice to the respondents, making it returnable on 09/06/2022.
( SMT. BHARATI DANGRE, J.) M.M.Salgaonkar