IN THE HIGH COURT OF JUDICATURE AT BOMBAY

CIVIL APPELLATE JURISDICTION WRIT PETITION NO. 3729 OF 2017 Maharashtra Krishna Valley Development Corporation Through its Executive Engg.

... Petitioner vs.

M/s. Bharat Construction & Anr.

... Respondents ....

Mr. R.S. Apte, Senior Advocate i/b Mr. N.N. Singh for the Petitioner. Mr. Abhijeet A. Desai for the Respondents.

....

Coram : A.A.Sayed, J.

Date : 12 April 2017 P.C. :

Learned Senior Counsel for the Petitioner, on instructions, seeks leave to withdraw the Petition with liberty to challenge the impugned order at the time of filing proceedings under Section-34 of the Arbitration and Conciliation Act, 1996.

The Writ Petition is allowed to be withdrawn with liberty as prayed.

(A.A.Sayed, J.) Sameer