← Library
Bombay High CourtWP/3741/2018disposed off

Mohammed Salim A. Shaikh v. The State Of Maharashtra And ORS.

2018-07-25Hon'Ble Shri Justice R. I. Chagla,Hon'Ble Shri Justice A.S. Oka3 pages

Sharayu Khot.

IN THE HIGH COURT OF JUDICATURE AT BOMBAY

CIVIL APPELLATE JURISDICTION WRIT PETITION NO. 3741 OF 2018 Mohammed Salim A. Shaikh

...Petitioner

Versus

The State of Maharashtra & Ors.

...Respondents

---------- Mr. Amol P. Mhatre, i/by Mr. Prasad P. Kulkarni, for the Petitioner.

Mrs. R.A. Salunkhe, AGP, for the Respondent No. 1. Mr. Ashutosh R. Gole, for the Respondent No. 2. ---------- CORAM :

ABHAY S. OKA AND RIYAZ I. CHAGLA, JJ.

Sharayu Pandurang Khot DATE : 25 July 2018 ORDER :

by Sharayu Pandurang Khot Date:

2018.07.27 17:33:39 +1200 1.

Not on board. Taken on board.

1 / 3

2.

Heard the learned Counsel appearing for the parties. 3.

The prayer made in this Petition is for directing the 1st to 5th Respondents to take action of demolition in respect of the alleged illegal construction made by the Respondent No. 6. 4.

The Affidavit filed by the 2nd Respondent of Shri. Somnath Soshte refers to an order of demolition passed by the said Officer on 14th June 2018 a copy of which is annexed with the Affidavit.

5.

The 2nd to 5th Respondents are bound to implement the said order in accordance with law as expeditiously as possible unless there is an order of Competent Court which prevents them from acting upon the said order. 6.

With the above directions, the Petition is disposed of.

2 / 3

7.

An action taken on the basis of the said order shall be communicated by the said Assistant Commissioner to the Petitioner within a period of three months from today. [RIYAZ I. CHAGLA J.] [ABHAY S. OKA, J.] 3 / 3