The New India Assurance Co. Ltd. Through Centralized Motor Tp Claims Hub, v. Smt. Usha Mohan Patil And ORS.
P.H. Jayani 12 CAF2977.16.doc
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
CIVIL APPELLATE JURISDICTION CIVIL APPLICATION NO. 2977 OF 2016 IN FIRST APPEAL (ST.) NO. 9630 OF 2016 The New India Insurance Company .....Applicant V/s.
Usha Mohan Patil & Ors.
....Respondents Mr. D.S. Joshi for the applicant.
Mr. Pramod Bhosale and Mr. Sharad Bhosale for R.Nos.1 and 2. CORAM: SMT. ANUJA PRABHUDESSAI, J.
DATED: 04th APRIL, 2018.
P.C.:
.
Heard the learned counsels for the respective parties. 2.
By this application, the applicant / insurance company has sought stay of the execution of judgment and award dated 10th August, 2015 passed by the District Judge-1 & Member, Motor Accident Claims Tribunal, Sangli in MACP No.77 of 2014, the Claims Tribunal has awarded compensation of Rs.7,44,000/- with interest @ 7.5% per annum to the respondent nos.1 & 2 herein from the date of filing of petition till realization of the amount.
3.
Mr. D.S. Joshi, learned counsel for the applicant states that the applicant / insurance company has deposited the entire amount before
P.H. Jayani 12 CAF2977.16.doc the Claims Tribunal. Statement is accepted.
4.
In the light of said statement, execution of judgment and award dated 10th August, 2015 passed by the District Judge-1 & Member, Motor Accident Claims Tribunal, Sangli in MACP No.77 of 2014 is stayed till the disposal of the appeal.
5.
Civil Application stands disposed of.
(SMT. ANUJA PRABHUDESSAI, J.)