← Library
Bombay High CourtCAF/3281/2008disposed off

The New India Assurance Co. Ltd. v. Sangramprasad Badariprasad @ Badariprasad Jaiswar And ANR

2022-07-25Hon'Ble Smt. Justice Anuja Prabhudessai2 pages

907 caf 3281-08.doc

IN THE HIGH COURT OF JUDICATURE AT BOMBAY

CIVIL APPELLATE JURISDICTION CIVIL APPLICATION NO. 3281 OF 2008 WITH CIVIL APPLICATION NO. 196 OF 2008 WITH INTERIM APPLICATION NO. 16698 OF 2022 IN FIRST APPEAL (ST) NO. 954 OF 2008 The New India Assurance Co. Ltd.

..Appellant/Applicant.

v/s.

Sangramprasad Badariprasad @ Badriprasad Jaiswar & Anr.

..Respondents None for the Appellant.

Mr. T.J.Mendon for the Respondent No.1-Org. Applicant. CORAM : ANUJA PRABHUDESSAI, J.

DATED : 25th JULY, 2022.

P.C.

1.

The appeal is rejected for non compliance of the conditional order dated 01.02.2008, which was further extended by order dated 29.02.2008, whereunder the Appellant was directed to deposit the amount under Workmen Compensation Act, within a period of four weeks, and produce certificate to that effect. 2.

It is seen that though the appeal is rejected, the civil applications are still pending. Civil application No. 196 of 2008 and 3281of 2008 stands disposed of in view of rejection of the appeal. Digitally signed by PRASANNA P SALGAONKAR Date:

2022.07.27 13:23:28 +0530 PRASANNA P SALGAONKAR 3.

Learned Counsel Mr. Mendon states that the amount has not been P P SALGAONKAR

907 caf 3281-08.doc deposited, hence he seeks leave to withdraw the application for withdrawal of the compensation.

4.

Leave granted. Application is dismissed as withdrawn. (ANUJA PRABHUDESSAI, J.) P P SALGAONKAR