M/S. Atul Projects India Pvt. Ltd. v. Lal Prasad Girijashankar Singh And ANR
682.14-ao+ FARAD CONTINUATION SHEET
IN THE HIGH COURT OF JUDICATURE AT BOMBAY.
CIVIL APPELLATE SIDE JURISDICTION.
APPEAL FROM ORDER NO.682 OF 2014 WITH APPEAL FROM ORDER NO.615 OF 2014 WITH APPEAL FROM ORDER NO.616 OF 2014 WITH APPEAL FROM ORDER NO.707 OF 2014 Office Notes, Office Memoranda of Coram, Appearances, court's orders or directions and Registrar's orders Court's or Judge's orders Mr. R. M. Vasudeo for the Appellant.
Mr. Surel S. Shah i/b. Sidharth Kapre for the Respondent No.1.
Mr. Vinod Mahadik for Municipal Corporation CORAM : K. K. TATED, J.
DATE : FEBRUARY 9, 2015 P.C.:
1.
Mentioned. Not on board. At the request of learned counsel for the Respondent No.1, the matters are taken on board for urgent orders. 2.
The learned counsel for the Respondent No.1 submits that as per order dated 22/12/2014 passed by this court (Coram : Mrs. Mridula R. Bhatkar, J.) the Designated Officer of Corporation has not passed any order till today. Hence, interim protection granted on 22/12/2014 to be continued.
Basavraj G Patil 1/2
682.14-ao+ 3.
Considering the submissions made by the learned counsel for the Respondent No.1 and other contesting parties, interim protection granted on 22/12/2014 to continue for a period of two weeks from the date of receipt of copy of order, that may be passed by the Designated Officer of the Respondent Corporation, by the parties/ Respondent No.1 JUDGE Basavraj G Patil 2/2