Sushilini Kishanrao Rathod And ANR v. The City And Industrial Development Corporation Of Maharashtra Ltd. Thr Chief Controller And ANR
903-wp-5826-2022
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
CIVIL APPELLATE JURISDICTION WRIT PETITION NO.5826 OF 2022 Sushilini Kishanrao Rathod & Anr.
...Petitioners
Versus
The City & Industrial Development Corporation of Maharashtra Ltd Thr. Chief Controller & Anr.
...Respondents
---- Mr.Laxman R. Shahapur for the Petitioners.
Mr.Nitin V. Gangal a/w Mr.Ashok D. Kadam and Ms.Prerna Shukla for Respondent No.1-CIDCO.
Mrs.M.P. Thakur, AGP for the Respondent-State. ---- CORAM : S.V. GANGAPURWALA & by NILAM SANTOSH KAMBLE Date: 2022.05.06 16:42:47 +0530 NILAM SANTOSH KAMBLE M.G. SEWLIKAR, JJ.
DATE : 6 MAY 2022 P.C:- .
Heard learned counsel for the Petitioners and the learned counsel for the Respondents.
2.
The learned counsel submits that the Petitioners would make an application/representation to CIDCO, with regard to the construction carried out by the Petitioners. In case such an Application is made within one week from today then the CIDCO may consider the said application/representation and decide on its own merits.
N.S. Kamble page 1 of 2
903-wp-5826-2022 3.
The Petitioners shall not carry out further construction, till the Application is decided 4.
In case the Application is not filed by the Petitioners within one week with CIDCO, then the Planning Authority may proceed further.
5.
The further steps be taken pursuant to the decision taken by the Planning Authority upon the representation of the Petitioners.
(M.G. SEWLIKAR, J.) (S.V. GANGAPURWALA, J.) N.S. Kamble page 2 of 2