← Library
Bombay High CourtCAA/495/2017

Rushi Constructions v. Bhardwaj Co.Operative Housing Society Limited And ORS

2019-02-18Hon'Ble Smt. Justice Pushpa Virendra Ganediwala2 pages

Sneha Chavan sr.14.caa.495.2017=.doc

IN THE HIGH COURT OF JUDICATURE AT BOMBAY

CIVIL APPELLATE JURISDICTION CIVIL APPLICATION NO.495 OF 2017 IN APPEAL FROM ORDER (ST.) NO.14726 OF 2017 Rushi Constructions ...Applicant

Versus

Bhardwaj Co-operative Housing Society Limited and ors.

...Respondents

---------- Mr.Rajiv Narula a/w Ms. Ekta Pandav I/b Jhangiani Narula and Associates for the applicants.

Mr. Abhishek Gupta I/b Mr.Ashok M. Saraogi for Respondent No.1. Ms. Oorja Dhond I/b Mr.Jernold Joseph Xavier for respondent no.2. ---------- CORAM :

PUSHPA V. GANEDIWALA, J.

DATE :

18th FEBRUARY 2019.

P.C. :

1. In this application, the delay of 19 days is sought to be condoned in filing appeal against the order dated 14.03.2017 in Notice of Motion No. 1659 of 2015 in L.C. Suit No. 1575 of 2015.

2. It is submitted that main contesting Respondents have already been served.

3. Heard learned Counsel for the parties.

1/2

Sneha Chavan sr.14.caa.495.2017=.doc

4. I am satisfied with the reasons mentioned in the application and the submissions on behalf of Applicant.

5. Delay of 19 days is condoned to present Appeal from order.

6. Civil Application is disposed of accordingly. No Costs.

7. Office is directed to place the matter as per CMIS date. [PUSHPA V. GANEDIWALA, J.] 2/2