Shelke Beverages Pvt. Ltd. Through Its Director Of Vishal B. Shelke v. Sub. Divisional Engineer, Chaskaman Irrigation Sub Div. No. 4, Shirur And ANR.
1/2 905.wp.5840.2019.doc
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
APPELLATE SIDE CIVIL JURISDICTION WRIT PETITION NO. 5840 OF 2019 Shelke Beverages Pvt. Ltd. Through Its Director Of Vishal B. Shelke ....Petitioner V/S Sub. Divisional Engineer, Chaskaman Irrigation, Sub Div. No. 4, Shirur & Anr.
....Respondents Mr. G. S. Godbole i/b. Ashok Tajane for the Petitioner. Ms. Shakuntala Wadekar for the Respondent No. 1 Ms. P. N. Diwan, AGP for the Respondent No. 2-State. CORAM :
A. A. SAYED & ANUJA PRABHUDESSAI, JJ.
DATED :
3rd March, 2020 P.C.:
By consent, we dispose of the Petition by passing the following order:
(i) The impugned order dated 15.04.2019 is set aside.
(ii) The Respondents shall issue show cause notice to the Petitioner within a period of 10 days from today. The Petitioner shall submit its Reply to the show cause notice within 10 days of the receipt of the show cause notice. (iii) The Chief Engineer shall hear the Petitioner. After hearing the Petitioner, the Chief Engineer shall pass AKN 1/2
2/2 905.wp.5840.2019.doc appropriate orders on the show cause notice.
(iv) It would be open for the Respondents to issue appropriate bills/revised bills, if necessary pursuant to the final orders.
2.
The Writ Petition to stand disposed of accordingly. (ANUJA PRABHUDESSAI, J.) (A. A. SAYED, J.) AKN 2/2