CIVIL APPELLATE JURISDICTION CIVIL APPLICATION No. 3088 OF 2009 IN FIRST APPEAL (St.) No. 17527 OF 2009 The New India Assurance Co. Ltd.
... Applicant Vs.
Dharmendra Shyamlal Gupta & Anr.
... Respondents Ms. Sayli Apte i/b. Prakash G. Lad, Advocate for the applicant. CORAM: MRS.MRIDULA BHATKAR, J.
DATE: 23rd January, 2018.
P.C.:
This Application is moved for condonation of delay of 356 days in filing the First Appeal.
2.
The learned counsel for the applicant/insurance company submitted that the application is served on respondent no. 1Dharmendra Shyamlal Gupta/original claimant. The learned counsel submitted that time was consumed in obtaining the permission of the higher authority.
3.
It appears from the judgment that opponent no. 2 did not appear to contest the claim and the insurance company has defence mainly on the point of quantum and negligence. Hence, notice against the respondent/owner is dispensed with. None present for 1 / 2
13.CAF3088_2009.doc respondent no.1 though served 4.
In view of the uncontroverted submissions, delay of 356 days is condoned.
5.
First Appeal be numbered and fixed for admission after 4 weeks.