Choice , A Partnership Firm v. Gangan Ace Developers
15-ARP-158-2023.DOC Gaikwad RD
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
CIVIL APPELLATE JURISDICTION ARBITRATION PETITION NO.158 OF 2023 M/s. Choice & Anr.
...Petitioners
Versus
M/s. Gagan Ace Developers & Ors.
...Respondents
Mr. Tejas P. Hartalkar for the Petitioners.
Mr. Dheeraj Patil i/b Mr. Dhupad S. Patil for Respondent No. 1.
CORAM
Dr. Neela Gokhale, J.
DATED:
3rd October 2023 PC:- 1.
Both the Counsels for the parties inform the Court that final arguments are over on 1st June 2023. The Arbitral Tribunal comprising of three arbitrators requires an extension of time to deliver the award. There is no request of the learned Arbitral Tribunal for extension of time on record. However, the parties have jointly requested for extension of time for passing of the award. 2.
I have heard both the Counsels and gone through the record and proceedings.
3.
I deem it necessary and expedient in the interest of justice that time be extended for a period of seven months from the date of 3rd October 2023
15-ARP-158-2023.DOC recording of the minutes of meeting dated 30th May 2023 held by the Arbitral Tribunal, Pune. Time to pass an award is, thus, extended till 31st December 2023.
4.
The Petition is disposed of accordingly.
(Dr. Neela Gokhale, J) 3rd October 2023