IN THE HIGH COURT OF JUDICATURE AT BOMBAY

CIVIL APPELLATE JURISDICTION CIVIL APPLICATION No. 2641 OF 2012 IN FIRST APPEAL (St.) No. 17737 OF 2012 The New India Assurance Co. Ltd.

... Applicant Vs.

Ramjeet Gaud & Ors.

... Respondents Ms. Poonam Mittal, Advocate for the applicant. Mr. T.J. Mendon, Advocate for the respondent no. 1. CORAM: MRS.MRIDULA BHATKAR, J.

DATE: 4th October, 2017.

P.C.:

This Application is moved for condonation of delay in filing the First Appeal.

2.

The learned counsel for the applicant submitted that there is a delay of 101 days in filing First Appeal and hence, the same be condoned.

3.

In view of the reasons mentioned in the Application, delay of 101 days is condoned.

4.

First Appeal be numbered.

5.

Civil Application is allowed and is disposed of accordingly. (MRIDULA BHATKAR, J.) 1 / 1