IN THE HIGH COURT OF JUDICATURE AT BOMBAY

CIVIL APPELLATE JURISDICTION CIVIL APPLICATION NO.816 OF 2019 IN APPEAL FROM ORDER NO.249 OF 2018 M/s. Baramati Infra Group Thr. Its Partner ...Appellant vs.

Shri. Laxman Nathu Mhatre And Ors.

...Respondents

......

Mr. Akhilesh Dubey, i/b. Mr. Nagendra Pratap Singh, for the Applicant. Mr. Rafeeq Peermohideen, a/w. Dipenshi Aboti, for Respondent No.6. .......

CORAM : S.C. GUPTE, J.

DATED : 23 SEPTEMBER 2019 P.C. :

.

Heard learned Counsel for the parties.

2.

This civil application seeks condonation of a delay of 19 days in filing restoration application in an appeal from order, which was dismissed for want of prosecution.

3.

For the reasons stated in the civil application, the delay is condoned and the Registry is directed to number the restoration application, namely, Civil Application (Stamp) No.16347 of 2019. Reply, if any, to be filed and served on the Applicant latest by 7 October 2019. The Applicant shall pay costs of this application of Rs.25,000/- to

sg 2/2 caa816-19.doc the Respondents in one set. Costs to be paid to the Advocates within two weeks from today. Costs to be condition precedent. 4.

Since the restoration application makes allegations against the Advocates, who were, at the relevant time, appearing for the Applicant, the Court requests the learned Advocates, Ms. Ranjan Rajguru and Mr. Salil Jaymal, to remain present in Court if they are so advised. The civil application to be placed for orders on 17 October 2019. A copy of this order be served on the above two Advocates. by Smita Gonsalves Date: 2019.09.26 14:14:12 +0530 Smita Gonsalves ( S.C. GUPTE, J. )