M/S. Soniya Construction And Development Thr. Its Sole Prop. Manish Morarji Palan v. M/S. Durga Builders And Developers
16-arp-154-2022-corrected.doc
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
CIVIL APPELLATE JURISDICTION ARBITRATION PETITION NO.154 OF 2022 M/s.Soniya Construction & Development Thr. Its Sole Prop. Manish Morarji Palan
...Petitioner
Vs.
M/s.Durga Builders & Developers
...Respondent
---- Mr.Anil Bagwe for the Petitioner.
Mr.Dheeraj Patil i/b Mr.Drupad Patil for the Respondent. ---- CORAM : C.V. BHADANG, J.
NILAM SANTOSH KAMBLE NILAM SANTOSH KAMBLE Date: 2022.09.26 17:50:46 +0530 DATE : 21 SEPTEMBER 2022 P.C.
.
This is an application under Section 29A of the Arbitration and Conciliation Act for extension of time for conclusion of the arbitral proceedings. The learned Arbitrator was appointed by an order dated 20 December 2018 by which the Arbitration proceedings were to be concluded within a period of six months. 2.
The learned counsel for the parties submit that the hearing in the Arbitration proceedings is concluded and the Arbitration proceedings are for pronouncement of the award. In that view of the matter, the time for passing of the award is extended by one month from today.
3.
The Petition is disposed of in the aforesaid terms. C.V. BHADANG, J.
This order is corrected as per speaking to the minutes of order dated 26 September 2022 N.S. Kamble page 1 of 1