IN THE HIGH COURT OF JUDICATURE AT BOMBAY
CIVIL APPELLATE JURISDICTION CIVIL APPLICATION NO. 847 OF 2018 IN FIRST APPEAL (ST) NO. 18354 OF 2017 Office Notes, Office Memoranda of Coram, appearances, Court's orders or directions and Registrar's orders Court's or Judge's orders.
Ms. Shalini Shankar for the Applicant.
Mr. Roshan Tannafor the Respondent Nos. 1 to 4.
CORAM: K.K.TATED, J.
DATED : 23/09/2019 P.C.
Heard learned Counsel for the parties.
Though, other Respondents are duly served, no one appeared on behalf of them, when the matter called out.
By this Civil Application, Applicant Insurance Company is seeking condonation of 147 days delay in filing First Appeal challenging the judgment and award dated 07.12.2016 passed by the MACT, Palghar in MACP No. 1588 of 2001.
The learned Counsel for Respondent No.
1 to 4 submits that Applicant has failed to disclose the sufficient cause for condonation of delay. Hence, there is no substance in the present Civil Application.
Sneha Chavan 1/2
47 caf 847-18=.odt Considering the submissions made by the learned Counsel for the Applicant and averments made in Civil Application, I am satisfied that Applicant has made out a case for allowing the Civil Application.
Hence, the following order is passed:
a) Delay in filing First Appeal, is condoned.
b) Civil Application stands disposed of accordingly.
c) No order as to costs.
(K.K.TATED, J.) Sneha Chavan 2/2