B.G. Shirke Construction Technology Pvt. Ltd. v. Maharashtra State Electricity Transmission Co. Ltd.
916-cap 30-19 in arp 6-16 psv
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
CIVIL APPELLATE JURISDICTION CIVIL APPLICATION NO.30 OF 2019 IN ARBITRATION PETITION NO.6 OF 2016 B.G. Shirke Construction Technology Pvt. Ltd. ..Applicant In the matter between B.G. Shirke Construction Technology Pvt. Ltd. ..Petitioner Vs.
Maharashtra State Electricity Transmission Co.Ltd. ..Respondent ----- Mr.Sukand Kulkarni for Applicant/Petitioner.
Mr.Abhijeet Joshi for Respondent.
----- CORAM :
G.S. KULKARNI, J.
DATE :
17th JULY, 2019 P.C.:
1.
Heard learned Counsel for the parties.
2.
This is an application filed under Section 29A(5) of the Arbitration and Conciliation Act, 1996 (for short, "the Act") whereby the applicant has prayed for extension of time limit for the arbitral tribunal to conclude the arbitral proceedings and publish an award. Learned Counsel for the respondent has no objection for the prayers as made in the application. It is agreed position at the bar that the last witness of the respondent is being cross-examined.
3.
In the circumstances, time to conclude the arbitral proceedings and pronounce an award is extended by three months from today. 4.
The application is disposed of in the above terms. No costs. [G.S. KULKARNI, J.]