The New India Assurance Company Limited v. Shri. Udaysingh Sadashivrao Dalvi And ANR.
18 CA 3416-15
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
CIVIL APPELLATE JURISDICTION CIVIL APPLICATION NO. 3416 OF 2015 IN FIRST APPEAL (ST.) NO. 20822 OF 2015 The New India Assurance Co. Ltd.
..... Applicant.
Vs.
Udaysingh Sadashivrao Dalvi & Ors.
..... Respondents.
Sandeep Jinsiwale for the Applicant.
Tejpal Ingale for Respondent No. 2.
......
CORAM
: K.K.TATED, J.
DATED : SEPTEMBER 17, 2019 P.C.
Heard Learned Counsel for the parties.
2.
By this Civil Application, the Applicant is seeking condonation of 52 days delay in fling the First Appeal challenging the Judgment and award dated 5th February, 2015 passed by the Motor Accident Claims Tribunal, Kolhapur in Motor Accident Claim Petition No. 272/2003. 3.
Considering the submission made by the learned counsel for the respondents and the averments made in Civil Application, I am satisfed that the Applicant has made out a case for allowing this Civil Application. Hence, the following order:
Laxmi Sontakke
18 CA 3416-15 a.
Delay in fling the First Appeal is condoned.
b.
Civil Application is disposed of accordingly. c.
No order as to costs.