IN THE HIGH COURT OF JUDICATURE AT BOMBAY

CIVIL APPELLATE JURISDICTION CONTEMPT PETITION NO. 546 OF 2022 Ankush Vitthal Wadekar ... Petitioner

Versus

The State of Maharashtra and Ors.

... Respondents WITH CONTEMPT PETITION NO. 370 OF 2021 YUGANDHARA SHARAD PATIL YUGANDHARA SHARAD PATIL Date: 2022.12.07 15:12:11 +0530 Baban Bhagu Walunj ... Petitioner

Versus

Uttam Patil, The Deputy Collector Rehabilitation,Pune & Ors.

... Respondents WITH CONTEMPT PETITION NO. 750 OF 2022 Ganpat Shripati Kadam (since deceased) through LRS. Balu Ganpat Kadam ... Petitioner

Versus

The State of Maharashtra and Ors.

... Respondents ****** Mr. Sachin Deokar for the Petitioner.

Mrs. R.M. Shinde AGP for the Respondent-State. ****** CORAM: R. D. DHANUKA AND M.M.SATHAYE JJ.

DATE : 6th DECEMBER 2022 P.C. :- 1.

Mrs. Shinde, learned AGP for the State, states that six weeks time may be granted to the respondents for allotment of the plot and to hand over possession thereof.

YSP 903(2) -CP-546-22&ors..doc 2.

Mr. Deokar, learned counsel for the petitioner states that plots will be identified by the petitioners which according to the petitioners are available and can be allotted to these petitioners. 3.

It is made clear that six weeks time is granted to the respondents to comply with the order from the date the petitioner identified the land. The respondent shall consider said land and allot such lands subject to availability and eligibility. 4.

Contempt Petitions are disposed of. No order as to costs. 5.

Place the matter on board for reporting 'Compliance' on 1st February 2023.

[M.M.SATHAYE,J.] [R. D. DHANUKA, J.]