M/S. Salvi Infrastructure Pvt. Ltd. And ANR v. The State Of Maharashtra And ANR
47.APPR.395.2017
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
CRIMINAL APPELLATE JURISDICTION CRIMINAL APPLICATION NO.395 OF 2017 IN CRIMINAL REVISON APPLICATION (STAMP) NO.436 OF 2017 M/s.Salvi Infrastructure Pvt.Ltd. and another Applicants versus The State of Maharashtra and another Respondents Ms.Tahera AR Qureshi for applicants.
T.RRM Roy for respondent no.2.
Ms.R.M.Gadhavi, APP, for State.
CORAM : PRAKASH D. NAIK, J.
DATE :
12th February 2018 PC :
1.
This is an application for condonation of delay. The applicant no.2 is convicted for offence under Section 138 of Negotiable Instruments Act. He has been sentenced to suffer imprisonment for one year and directed to pay compensation of Rs.1,66,218/-. 2.
The applicants have stated that there is delay of about 199 days in filing the revision application. The advocate for respondent no.2 disputes the calculation and submitted that there is delay of about 330 days. Be that as it may, for the reasons stated in the application and in the interest of justice, the delay is required to be condoned. Accordingly, Criminal Application No.395 of 2017 is allowed and delay is condoned.
(PRAKASH D. NAIK, J.) MST