← Library
Bombay High CourtIA/295/2022disposed off

Shri. Shital Neminath Bindage Decd Thru Lhrs v. The Chief Engineer Maharashtra State Electricity Distribution Company Ltd., Adn ANR

2022-10-07Hon'Ble Shri Justice Madhav J. Jamdar2 pages

19-ia-295-2022 in wp-3204-2018.doc Pallavi

IN THE HIGH COURT OF JUDICATURE AT BOMBAY

CIVIL APPELLATE JURISDICTION PALLAVI MAHENDRA WARGAONKAR PALLAVI MAHENDRA WARGAONKAR Date: 2022.10.10 17:15:04 +0530 INTERIM APPLICATION NO.295 OF 2022 IN WRIT PETITION NO. 3204 OF 2018 Shri. Shital Neminath Bindage Decd Thru LRs.

...Applicant

Versus

The Chief Engineer Maharashtra State Electricity Distribution Company Ltd., and Anr.

...Respondents

Ms. Pavitra Manesh i/b Meelan Topkar, for the Applicant. Smt. Anjali R. Shiledar - Baxi, for Respondent Nos.1 and 2. CORAM : MADHAV J. JAMDAR, J.

DATE : 7 th OCTOBER, 2022 P.C. :

1.

Heard Ms. Pavitra Manesh, the learned counsel appearing for the Petitioner and Smt. Anjali Shiledar, the learned counsel appearing for Respondent Nos.1 and 2. Interim application is for bringing on record the legal heirs of the original petitioner no.1. Ms. Manesh submits that the deceased petitioner no.1 passed away on 18th August 2020 and the present application has been filed on 4th October 2021. She submits that the Supreme Court has kept in abeyance limitation period in view of Covid 1/2

19-ia-295-2022 in wp-3204-2018.doc pandemic. Same was kept in abeyance since March 2020 till 20th August 2021. Thus, there is no delay in filing this application. Application is allowed in terms of prayer clause 5(ii). Amendment to be carried out within a period of 14 days from today.

(MADHAV J. JAMDAR, J.) 2/2