IN THE HIGH COURT OF JUDICATURE AT BOMBAY

CIVIL APPELLATE JURISDICTION CIVIL APPLICATION NO. 4171 OF 2016 IN FIRST APPEAL ST. NO. 24194 OF 2016 The New India Assurance Co. Ltd.

...Applicant

Versus

Smt.Shalleishdevi Shivsaran Singh & Ors.

...Respondents

......

Ms.Pooja Yadav i/b. Mr.D.R.Mahadik for the Applicant. Mr.T.J.Mendon for Respondent Nos. 1 to 3.

......

CORAM:

V.G.BISHT, J.

DATE:

15TH JANUARY, 2020 PC:- 1.

This Application is moved for condonation of delay of 248 days in preferring the First Appeal.

2.

Heard the learned Counsel for the applicant.

3.

The learned Counsel for respondent Nos.1 to 3 submits that if the delay is condoned, some costs may be imposed on the applicant.

4.

In view of submissions made by learned Counsel and the reasons mentioned in paragraph Nos. 2 and 3 of the Civil Trupti 1/2

47-CAF-4171-2016.DOC Application, delay of 248 days in filing the Appeal stands condoned, subject to payment of costs of Rs. 1,000/-. The applicant to pay a sum of Rs.1,000/- to the office of Maharashtra State Legal Services Authority. On depositing the costs, the Appeal be registered in accordance with law.

5.

Civil Application is disposed of.

(V.G.BISHT, J.) Trupti 2/2