IN THE HIGH COURT OF JUDICATURE AT BOMBAY

CIVIL APPELLATE JURISDICTION CIVIL APPLICATION NO. 257 OF 2018 IN FIRST APPEAL (ST) NO. 24031 OF 2017 New India Insurance Co. Ltd.

..Applicant v/s.

Gita Ajay Mulik & Ors.

..Respondents Mr. Mayuri Dhumal i/b. Milind More for the Applicant/Appellant Mr. Nagesh Chavan for the Respondent.

CORAM : SMT. ANUJA PRABHUDESSAI, J.

DATED : 17th APRIL, 2018.

P.C.

1.

Heard. By this application, the applicant has sought to condone the delay of 42 days in challenging the judgment and award dated 13th March, 2017 passed by the MACT, Sangli in MACP No. 8 of 2015. 2.

In my considered view, the reasons stated in para 3 of the application, constitute sufficient ground to condone the delay. Hence the delay is condoned.

3.

Application is disposed.

4.

Appeal be registered after removal of office objections, if any. (ANUJA PRABHUDESSAI, J.) pps