M/S R.R. Enterprises, A Proprietrship Firm, Through Its Proprietor v. The State Of Maharashtra Through The Secretary And ORS.
spb/ 912caw1797wp7334-18.odt
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
CIVIL APPELLATE JURISDICTION CIVIL APPLICATION NO. 1797 OF 2018 IN WRIT PETITION NO. 7334 OF 2018 M/s. R. R. Enterprises ... Applicant/Petitioner.
V/s.
The State of Maharashtra & Ors.
... Respondents.
--- Mr. Y. B. Lengare, Advocate for the Applicant/ Petitioner. Mr. V. S. Gokhale, "B" Panel Counsel for the State. --- CORAM : R. M. BORDE AND PRITHVIRAJ K.CHAVAN,JJ.
DATE : AUGUST 16, 2018 PC :
Applicant is praying for extension of time in respect of lifting of minor mineral / sand collected by him under the authorization issued by the State Authority. This court while allowing the petition, permitted the petitioner to remove sand stock within the period of two weeks from the date of the order I.e 2nd August, 2018. The petitioner contends that the order issued on 04.08.2018 by the Additional Collector was served on the petitioner on 05.08.2018 at 7.30 p.m. and the said order remained valid upto 16.08.2018. The Petitioner was, thus, permitted only 10 days time for removal of the by Shalikram Pralhadrao Borey Date: 2018.08.16 19:49:24 +0530 Shalikram Pralhadrao Borey Borey 1/2
spb/ 912caw1797wp7334-18.odt sand stock. The petitioner contends that the authorization issued by the Dy. Collector on 04.07.2018 is not in conformity with the direction issued by this court while disposing of the writ petition.
Considering the above, after hearing the learned counsel for the parties, we direct the Respondent to permit the petitioner to lift the remaining sand stock in terms of the order passed by us on 2nd August, 2018 upto 23.08.2018 and time is extended. It is clarified that no further extension shall be granted.
Civil application is disposed of in the above terms. (PRITHVIRAJ K. CHAVAN, J.) (R. M. BORDE,J.) .....
Borey 2/2