IN THE HIGH COURT OF JUDICATURE AT BOMBAY

CIVIL APPELLATE JURISDICTION CIVIL APPLICATION NO.186 OF 2016 IN APPEAL FROM ORDER (STAMP) NO.24677 OF 2015 WITH APPEAL FROM ORDER (STAMP) NO.24677 OF 2015 Dharamraj Deo Narayan Yadav & Anr.

...Applicants

Versus

Slum Rehabilitation Authority and Ors.

...Respondents

.....

Ms Asha Ram Shukla for the Applicants.

Mr. Anoop Patil for the Respondent No.1.

Mr. Ashutosh Shukla i/b. Mr. M.U. Pande for the Respondent No.2. Mr. J.N. Jayle for the Respondent No.3.

CORAM : SMT. ANUJA PRABHUDESSAI, J.

DATED: 26th MARCH, 2018.

P.C.:- By this application, the Applicants have sought to condone the delay of 24 days in filing the Appeal.

2.

Heard the learned counsel for the Applicants and the learned counsels for the Respondents. The learned counsel for the Respondent Nos.3 and 4 submits that the delay is of 34 days. He submits that certified copy was ready on 3.10.2015 and not on 10.8.2015. Even if it is considered that delay is of 34 days, in my Megha 1/2

Megha 11_caa_186_2018.doc considered view the reasons given in paragraph 3 of the application, constitute sufficient grounds to condone the delay. Under the circumstances, the delay in filing the appeal is condoned. The Appeal be registered.

3.

The application stands disposed of.

4.

Mr. Anoop Patil, the learned counsel waives service for the Respondent No.1. Mr. Ashutosh Shukla, the learned counsel waives service for the Respondent No.2. Mr. J.N. Jayle, the learned counsel waives service for the Respondent No.3. Place the appeal for admission on 2.5.2018, subject to removal of office objections, if any. (SMT. ANUJA PRABHUDESSAI, J.) Megha 2/2