Smt.Ramalinga Gudse And ANR. v. Union Of India Thr.The General Manager,
9- CAF 1162 of 2018.doc
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
CIVIL APPELLATE JURISDICTION CIVIL APPLICATION No. 1162 OF 2018 IN FIRST APPEAL (ST) No. 25352 OF 2017 Smt.Ramalinga Gudse and Anr.
...Applicants Vs.
Union of India, through the General Manager
...Respondent
Mr.Kuldeep Singh for the Applicants Mr. T.J. Pandian for Respondent
CORAM:
K.K. TATED, J.
DATED:
JULY 23, 2019 P.C. :
1.
Heard learned counsel for the parties.
2.
By this civil application, the Applicant, Original Claimant is seeking condonation of 234 days' delay in filing the First Appeal, challenging the judgment and award dated 4th October, 2016 passed by the Railway Claim Tribunal, Mumbai Bench, Mumbai in Claim No. OA/IIu/MCC/2011/0118 of 2011.
3.
Considering the submissions made by the learned counsel for the Applicant and the averments made in the civil application, I am satisfied that the Application has made out a case for allowing this civil application.
Tikam 1/
9- CAF 1162 of 2018.doc 4.
Hence, following order.
(a) Delay in filing the First Appeal is condoned.
(b) Civil Application stands disposed of.
(c) No order as to costs.
(K. K. TATED, J.) Tikam 2/