← Library
Bombay High CourtCAF/210/2017allowed

Bombay Electricity Supply And Transport v. Smt. Nuzhat Rehan Khan And ORS.

2018-03-21Hon'Ble Smt. Justice Anuja Prabhudessai1 pages

Megha 21_caf_210_2017.doc

IN THE HIGH COURT OF JUDICATURE AT BOMBAY

CIVIL APPELLATE JURISDICTION CIVIL APPLICATION NO.210 OF 2017 IN FIRST APPEAL (STAMP) NO.26579 OF 2016 Bombay Electricity Supply and Transport ...Applicants/Appellant

Versus

Smt. Nuzhat Rehan Khan & Ors.

...Respondents

.....

Ms Kavita Anchan for the Applicant/Appellant. Mr. Bharat Gadhvi i/b. Mr. Surendra Sonawane for the Respondents. CORAM : SMT. ANUJA PRABHUDESSAI, J.

DATED: 21st MARCH, 2018.

P.C.:- By this application, the Applicant has sought to condone the delay of 167 days in challenging the judgment and award dated 1.12.2015 passed by the Motor Accident Claims Tribunal, Mumbai in Application No.743 of 2008.

2.

In view of the reasons stated in paragraph 15 of the application, which in my considered view constitute sufficient grounds, delay of 167 days in filing the appeal is condoned. The appeal be registered. The application stands disposed of. (SMT. ANUJA PRABHUDESSAI, J.) Megha 1/1