CIVIL APPELLATE JURISDICTION ARBITRATION PETITION(St.) NO. 25861 OF 2019 M/s. SPN Roads Infrastructure Pvt. Ltd. & Anr. ... Petitioners V/s.

Government of Maharashtra ... Respondent Mr. Shivam P. Srivastav i/b. Mr. Jaideep Thakkar for the petitioners. Mr. A.R. Patil, Addl. G.P. for the respondent. CORAM : G.S.KULKARNI, J.

DATE : 16 October, 2019 P.C.:

Heard learned counsel for the petitioners and learned counsel for the respondent.

2.

This is a Petition filed under section 29-A of the Arbitration and Conciliation Act, 1996 whereby the petitioners are seeking extension of the mandate of the arbitral tribunal to conclude the arbitral proceedings and make an award.

3.

It is stated that the arguments of the petitioners are concluded and only the argument on behalf of the respondent would be heard. Learned counsel for the respondent has no objection for the mandate to be extended. 4.

In the facts and circumstances of the case, it is in the interest of justice 1/2

6.ARPSt25861_2019.doc that the time to conclude the arbitral proceedings and make an award is extended by a period of six months from 16 November 2019. 5.

Petition is disposed of in the above terms. No costs. (G.S.KULKARNI, J.) 2/2