Principal General Manager, Bsnl Bharat Sachar Nigham Ltd. And ANR. v. M/S. Roshan Enterprises Through Its Prop. Mr. J. V. Kulkarni
1/1 ara-32-14.doc
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
CIVIL APPELLATE JURISDICTION ...
ARBITRATION APPEAL NO.32 OF 2014 ...
Principal General Manager, BSNL and anr.
...Appellants v/s.
M/s.Roshan Enterprises
...Respondent
...
Ms.Neeta Vinay Masurkar for the Appellants.
Mr.Makarand P.Panchakshari for the Respondent. ...
CORAM : A.A. SAYED, J.
DATED : 11 APRIL 2017 P.C.:
Learned Counsel for the parties, on instructions, are agreed to the following order being passed:
ORDER
The Appellant shall pay to the Respondent the principal amount of Rs.84,990/- within a period of six weeks from today in full and final settlement of the claim of the Respondent. In the event the amount is not paid within the stipulated period, liberty to the Respondent to move this Court.
2.
The Appeal is disposed of in the aforesaid terms. (A.A. SAYED, J.) Uday.P.Kambli 1/1