← Library
Bombay High CourtCAF/3709/2015disposed off

The New India Assurance Co. Ltd. Through Mumbai Regional Offie-I v. Mr. Suvalal Motilal Surana And ORS.

2015-10-28Hon'Ble Mrs. Justice Mridula Bhatkar2 pages

prod-9-caf-3709-2015.doc FARAD CONTINUATION SHEET

IN THE HIGH COURT OF JUDICATURE AT BOMBAY

CIVIL APPELLATE JURISDICTION CIVIL APPLICATION NO.3709 OF 2015 IN FIRST APPEAL (ST.) NO.11520 OF 2015 Office Notes, Office Memorandum of Coram, appearances, Court's orders or directions and the Registrar's orders Court's or Judge's orders Mr. S.S. Jinsiwale, for the Appellant.

CORAM: MRS.MRIDULA BHATKAR, J.

DATED: 28th OCTOBER, 2015 .

Not on board. Upon mentioning taken on board.

2.

The learned counsel for the Applicant/Assurance Company prays that the operation and execution of the judgment and award dated 16th December, 2014 passed by the learned Motor Accident Claims Tribunal, Nashik in M.A.C.P. No. 257 of 2005 be stayed. He submits that the execution proceeding are initiated against the Assurance Company. He submitted that the Assurance Company is ready to deposit the amount.

Vishal 1 of 2

prod-9-caf-3709-2015.doc 3.

Considering the above submissions, the effect and implementation of the impugned judgment and award dated 16th December, 2014 is hereby stayed for eight weeks subject to the Assurance company to deposit the entire amount along with the interest accrued thereon within six weeks before the Tribunal.

4.

Accordingly the Civil Application stands disposed of.