Executive Engineer, Kadava Kadava(Cannel) Project, Nashik v. Subhash Yashawant Wagh And ORS.
(21)-IA-4359-21.doc.
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
CIVIL APPELLATE JURISDICTION INTERIM APPLICATION NO.4359 OF 2021 IN FIRST APPEAL STAMP NO.25228 OF 2021 Executive Engineer, Kadava Kadava (Cannel) Project, Nashik ..Applicant/Appellant
Versus
Subhash Yashawant Wagh & Ors.
..Respondents Ms. Chaitrali A. Deshmukh, for the Applicant/Appellant. Mr. Sachin Gite, for the Respondent.
Mr. A. R. Patil, AGP for the Respondent/State. CORAM : KISHORE C. SANT, J.
DATE : 11th JANUARY, 2024 P.C.
1.
This application is filed for condonation of delay of three years twenty two days caused in filing First Appeal challenging the judgment and award dated 30.08.2018 passed by the Civil Judge, Senior Division, Nashik in Land Acquisition Reference No.369 of 2010.
2.
Heard the parties.
3.
For the reasons stated, the application stands allowed. Delay stands condoned.
4.
Application stands disposed of.
[KISHORE C. SANT, J.] BGP.