← Library
Bombay High CourtWP/12026/2017disposed off

Dow Chemical International Pvt. Ltd. v. Union Of India And ORS.

2017-11-03Hon'Ble Shri Justice S.J. Kathawalla2 pages

Nitin 1 / 2 MNOB-WP-12026-2017.sxw

IN THE HIGH COURT OF JUDICATURE AT BOMBAY

CIVIL APPELLATE JURISDICTION WRIT PETITION NO. 12026 OF 2017 Dow Chemical International Pvt. Ltd.

...

Petitioner

Versus

Union of India and Ors.

...

Respondents Mr. A.G. Damle, Sr. Adv. a/w. Mr. Amit Singh i/b.Mr. Santosh Sawant for the Petitioner.

Mr. Suresh Kumar for the Respondent.

CORAM : S.J. KATHAWALLA, J.

DATED : 3RD NOVEMBER, 2017 P.C.:

1.

Not on board. Upon mentioning, taken on board. 2.

A grievance is made by the learned Senior Advocate appearing for the Petitioner that before expiry of the statutory period of filing an Appeal from the order passed by the Provident Fund Authority, the account of the Petitioner being Account No.2753006 of Citi Bank, D.N. Road Branch, Mumbai has been attached. 3.

In view thereof, the attachment levied by the Provident Fund Authority is set aside.

4.

The Petitioner shall be at liberty to file an Appeal along with Interim Application within a period of two weeks from today. Upon such Interim Application being filed, the Appellate Authority shall decide and dispose off the same within a

Nitin 2 / 2 MNOB-WP-12026-2017.sxw period of two weeks thereafter.

4.

In view of this order, the above Writ Petition stands disposed off. ( S.J.KATHAWALLA, J. )