Devi Construction Llp Thou Its Partner Vinod Baney v. State Of Maharashtra And ORS
926-ASWP-13382-2023.DOC Sumedh
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
CIVIL APPELLATE JURISDICTION WRIT PETITION NO. 13382 OF 2023 Devi Construction LLP
...Petitioner
Versus
State of Maharashtra & Ors
...Respondents
Mr Dormaan J Dalal, for the Petitioner.
Mrs MP Thakur, AGP, for Respondent Nos 1 to 3-State Mr Rohit Sakhdeo, for Respondent Nos 4 & 5-PCMC.
CORAM
G.S. Patel & Kamal Khata, JJ.
DATED:
17th January 2024 PC:- 1.
Mentioned out of turn.
2.
Mr Dalal states that there is an appeal under Section 47 of the Maharashtra Regional & Town Planning Act, 1966 filed before the Minister on 18th December 2018. It is still pending. 3.
We request the Hon'ble Minister to take up the Appeal and dispose of it in accordance with law at the earliest possible. It is only for this reason that this present Writ Petition had to be filed. The appeal is in regard to the proposed extension to an existing hospital. While we cannot impose a time limit since the appeal is before the Digitally signed by SUMEDH NAMDEO SONAWANE Date:
2024.01.18 10:55:33 +0530 SUMEDH NAMDEO SONAWANE 17th January 2024
926-ASWP-13382-2023.DOC Hon'ble Minister, we do request that the matter be given all possible priority.
4.
We dispose of the matter with these directions with liberty to the Petitioner to apply.
(Kamal Khata, J) (G. S. Patel, J) 17th January 2024