The Municipal Corporation Of Gr. Mumbai Through Best Undertaking, v. Smt. Nirmala Sandeep Gavhane And ORS.
1/2 27-CA-2473-2016.odt
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
BEFORE THE NATIONAL LOK ADALAT CIVIL APPELLATE JURISDICTION CIVIL APPLICATION NO.2473 OF 2016 IN FIRST APPEAL (ST) NO.32356 OF 2015 The Municipal Corporation of Gr.Mumbai Through the General Manager of Best Undertaking ...
Applicant.
V/s.
Nirmala Sandeep Gavhane & Ors.
...
Respondents.
Ms. Kavita Anchan with Mr. Vishal Dhende i/by M.V.Kini & Co., Advocates for the Applicant.
Mr. B.M.More, Advocate for the Respondents.
CORAM :
S.K.SHINDE J (HEAD OF THE PANEL).
S.R. SALKUTE, OFFICER ON SPECIAL DUTY, MEMBER AND A.M.CHANDEKAR, PROTHONOTARY & SENIOR MASTER, MEMBER.
DATED :
22nd APRIL 2018.
P.C. :
1] This application is preferred by the Municipal Corporation of Greater Bombay through the General Manager, BEST Undertaking seeking condonation of delay of 129 days caused in preferring the appeal against the award dated 12.3.2015 passed in the Motor Accident Claim Application No.214 of 2009.
Shivgan
2/2 27-CA-2473-2016.odt 2] Heard the learned counsel for the Applicant and the learned counsel for the Respondents. Pending this application, the Original Respondent No.4 (father of the Deceased) died on 3.1.2016. Mr. More, the learned counsel for the Respondents submits that other Respondents are the legal representatives of the deceased. Thus, in view of this fact, Applicant is directed to amend the Civil Application and cause-title of Appeal forthwith.
3] Having shown sufficient cause, delay is condoned. Application is allowed.
(S.K.SHINDE, J) (S.R.SALKUTE) (A.M.CHANDEKAR) HEAD OF THE PANEL MEMBER MEMBER Shivgan