IN THE HIGH COURT OF JUDICATURE AT BOMBAY
CIVIL APPELLATE JURISDICTION WRIT PETITION NO. 14122 OF 2023 Samji Navla Kurada and Ors.
... Petitioners V/s.
Smt. Mangaliben Radka Kurada and Ors.
... Respondents Mr. Mandar Soman for the Petitioners Adv. Manoj Kumar a/w. Adv. Vishal Rathod for the Respondent Nos. 1 to 3 Adv. H. S. Venegavkar a/w. Adv. S. Thorat for the Respondent-UT. CORAM : NITIN JAMDAR & M. M. SATHAYE, JJ.
DATED : 14 MARCH, 2024 P.C.:
1.
On 28 February 2024, the following order was passed: ".
Objection is lodged by the Respondent Nos. 1 to 3 before the Collector, Silvassa as regarding the disbursement of compensation of the land in question. Objection is of 3 July 2021. The learned Counsel for the Petitioners states that in view of this objection, the compensation is not being disbursed.
2. The learned Counsel for the Union Territory is not present."
2.
Learned Counsel for the Respondent-Union Territory states that akn 1/2
2.WP.14122.2023.doc the decision would be taken with a period of 8 weeks. Learned Counsel for the Petitioners states that the period of 8 weeks is unduly long. 3.
Considering that the objection was lodged on 3 July 2021, the decision be taken by the Respondent-Union Territory within a period of 4 weeks from today.
4.
Writ Petition is accordingly disposed of.
(M. M. SATHAYE, J.) (NITIN JAMDAR, J.) akn 2/2