New India Assurance Co. Ltd. v. Smt. Ushadevi Shivshyam Mishra And ORS.
21 CAF 1501 OF 2017.odt vks
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
CIVIL APPELLATE JURISDICTION CIVIL APPLICATION NO.1501 OF 2017 IN FIRST APPEAL (ST) NO.33260 OF 2016 New India Assurance Co.Ltd.
...
Appellant V/s.
Ushadevi Shivshyam Mishra and ors ...
Respondents Ms. PoonamMital, for the appellant.
Mr. T. J. Mendon, for respondent Nos. 1 to 3. CORAM : DR.SHALINI PHANSALKAR-JOSHI, J.
DATE : 25th OCTOBER, 2018.
P.C. :
1] Heard learned counsel for the appellant and respondent. 2] This application is for condonation of delay of 82 days in filing the First Appeal. For the reasons stated in the application as sufficient cause is made out, the delay is condoned. Application is allowed with no order as to costs.
3] Application is disposed off accordingly.
[DR.SHALINI PHANSALKAR-JOSHI, J.] 1/1