Vijay Mansukhlal Goradia And ANR. v. The Municipal Corporation Of Greater Mumbai Through The Executive Engineer, Mumbai
33-IA-16975-23 In RPFST-29747-23.doc
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
CIVIL APPELLATE JURISDICTION INTERIM APPLICATION NO.16975 OF 2023 IN REVIEW PETITION (ST) NO.29747 OF 2023 Vijay Manshukhlal Goradia & Anr.
.... Applicants V/s.
The Municipal Corporation of Gr. Mumbai, Thr. The Executive Engineer, Mumbai .... Respondent by NILAM SANTOSH KAMBLE Date: 2024.03.22 17:21:57 +0530 NILAM SANTOSH KAMBLE ---- Mr.Drupad Sopan Patil, for the Applicants.
Mr.Santosh Parad, for the Respondent.
---- CORAM : SHIVKUMAR DIGE, J.
DATE : 21st MARCH 2024 P.C:- .
Heard learned counsel for the Applicants and the learned counsel for the Respondents.
2.
The learned counsel for the Respondent tendered copy of the reply, it is taken on record.
3.
Considering the submission of both learned counsel and the reasons mentioned in the Application, the delay of 6 years and 7 days for filing the Appeal is condoned. The Application is allowed and disposed of.
4.
The Appeal be registered.
(SHIVKUMAR DIGE, J.) N.S. Kamble page 1 of 1