The New India Assurance Co. Ltd. v. Shri. Shantosh Raghunath Mane And ANR.
14 CA 1934-14
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
CIVIL APPELLATE JURISDICTION CIVIL APPLICATION NO. 1934 OF 2014 IN FIRST APPEAL (ST.) NO. 34532 OF 2013 The New India Assurance Co. Ltd.
..... Applicant.
Vs.
Santosh Raghunath Mane & Anr.
..... Respondents.
......
S. M. Dange for the Applicant.
Vishwambhar for Respondent No. 1.
......
CORAM
: K.K.TATED, J.
DATED : SEPTEMBER 17, 2019 P.C.
Heard Learned Counsel for the parties.
2.
By this Civil Application, the Applicant is seeking condonation of 51 days delay in filing the First Appeal challenging the Judgment and award dated 19th August, 2013 passed by the Commissioner for Workmen'
s Compensation and the Judge, 2nd Labour Court, Mumbai in application (W.C.A.) No. 3/C-1/2009 holding that the Respondents/Original Claimants are entitled to sum of Rs. 4,53,527/- by way of compensation with interest @ 12% p.a.
3.
Considering the submission made by the learned counsel for the Applicant and the averments made in Civil Application, I am satisfied that the Applicant has made out a case for allowing this Civil Application. Hence, the following order: Laxmi Sontakke
14 CA 1934-14 a.
Delay in filing the First Appeal is condoned. b.
Civil Application is allowed.
c.
Nor order as to costs.
(K.K.TATED, J.) Laxmi Sontakke