The Executive Engineer, Nandur Madhameshwar Project v. Mr. Chandrabhan Sukdeo Gade And ANR.
P.H. Jayani 27(B) IA1853.2019.doc
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
CIVIL APPELLATE JURISDICTION CIVIL APPLICATION NO.1853 OF 2019 IN FIRST APPEAL (ST.) NO.32670 OF 2018 The Executive Engineer, Nandur Madhameshwar Project, Nashik .... Applicant v/s.
Chandrabhan Sukdeo Gade and anr.
.... Respondents Mr. Sarfaraj J. Shaikh i/b. Ms. Chaitrali Deshmukh for the Applicant. Ms. Tanaya Goswami, AGP for the State.
CORAM: SMT. ANUJA PRABHUDESSAI, J.
DATED : 19th JULY, 2022.
P. C. :- .
Learned counsel for the Applicant states that the entire amount of compensation as per the impugned judgment and award dated 17/10/2014 has been deposited before the Reference Court. 2.
In the light of said statement, execution and implementation of the impugned judgment and award is stayed pending hearing of the Appeal.
3.
Civil Application stands disposed of.
Digitally signed by PREETI H JAYANI Date:
2022.07.26 16:31:14 +0530 (SMT. ANUJA PRABHUDESSAI, J.) PREETI JAYANI 1/1