IN THE HIGH COURT OF JUDICATURE AT BOMBAY

CIVIL APPELLATE SIDE JURISDICTION CIVIL APPLICATION NO.694 OF 2018 IN CIVIL REVISION APPLICATION [STAMP] NO.32765 OF 2018 Hayyat Badshah ] Applicant Vs.

Rukmani Krishna Turbhekar ] Respondent .....

Mr. Joel D'Souza i/b I.R. Qureshi, for Applicant. Mr. R.M. Haridas, for Respondent No.1.

.....

CORAM : R.G. KETKAR, J.

DATE : 4th JANUARY, 2019.

P.C.

Heard Mr. D'Souza, learned Counsel for the applicant and Mr. Haridas, learned Counsel for respondent No.1. 2.

This is an application for condonation of delay of 33 days caused in filing Civil Revision Application. For the reasons set out in the application, I am satisfied that the applicant has made out a sufficient cause for condoning delay. Hence, C.A is allowed in terms of prayer clause (a) with no order as to costs.

[R.G. KETKAR, J.]