Sou. Anjana Mallikarjan Mane v. The Manager, Bharat Petroleum Corporation Ltd, And ORS.
11-ASIA-2177-2019 IN WP-2636-2018.DOC Ashwini
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
CIVIL APPELLATE JURISDICTION INTERIM APPLICATION NO. 2177 OF 2019 IN WRIT PETITION NO. 2636 OF 2018 Anjana Mallikarjan Mane ...Applicant In the matter between Anjana Mallikarjan Mane
...Petitioner
Versus
The Manager, Bharat Petroleum Corporation Ltd & Ors
...Respondents
Ms Rakhee Dube, i/b Abhiman D Patil, for the Applicant. Mr SR Page, for Respondent No. 1.
Mr RP Kadam, AGP, for for Respondents Nos. 2 & 3.
CORAM
G.S. Patel & Madhav J. Jamdar, JJ.
DATED:
23rd March 2022 PC:- ASHWINI HULGOJI GAJAKOSH by ASHWINI HULGOJI GAJAKOSH Date: 2022.03.24 18:58:35 +0530 1.
The Interim Application seeks restoration of the Writ Petition which was dismissed on 18th June 2019. The Interim Application was filed on 18th October 2019. The dismissal was for non prosecution. The Interim Application explains that the dismissal was due to an oversight on the part of the Applicant's Advocate. We accept the explanation and condone the delay of 157 days. This 23rd March 2022
11-ASIA-2177-2019 IN WP-2636-2018.DOC delay is also been explained in paragraphs 4 and 5 of the Interim Application. The Interim Application is made absolute in terms of prayer clauses (a) and (b). The Writ Petition is restore to file. There will be no order as to costs.
2.
List the matter on 30th March 2022.
(Madhav J. Jamdar, J) (G. S. Patel, J) 23rd March 2022