← Library
Bombay High CourtCARAP/19/2019disposed off

Madhubhan Motors Pvt Ltd v. Manmohan Bhimsain Goyal And ANR

2019-01-14Hon'Ble Shri Justice B.P. Colabawalla2 pages

Ladda

IN THE HIGH COURT OF JUDICATURE AT BOMBAY

ORDINARY ORIGINAL CIVIL JURISDICTION COMMERCIAL ARBITRATION APPLN.(Lodging) No. 1 of 2019. M/s Madhubhan Motors Pvt. Ltd.

..Applicant.

Vs Manmohan Bhimsain Goyal & Anr ..Respondents.

Mr. Devashish Godbole I/by Parinam Law & Associates for the Applicant.

Ms. Nehal Soni, Advocate for the Respondents. CORAM : B. P. COLABAWALLA, J.

DATED :- 14th JANUARY, 2019.

P.C. :

1) This arbitration petition has been filed under Section 29A of the Arbitration and Conciliation Act, 1996 for seeking an extension of time for a period of six months to complete the arbitral proceedings and pass a final award. The learned Advocate appearing on behalf of the Respondents has fairly stated on instructions that the respondents have no objection if the time is so extended.

2) In these circumstances, the time to complete the arbitration proceedings and pass a final Award is extended by a period of six months from today.

1/2 4-carap-1-19.doc

3) Arbitration Application is disposed of in the aforesaid terms. There shall be no order as to costs.

(B.P. COLABAWALLA, J.) 2/2 4-carap-1-19.doc