Century Rayon Employees Consumers Co-Operative Society Ltd And ANR v. State Of Maharashtra And 2 ORS
spb/ 30wp091-19-2.odt
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
ORDINARY ORIGINAL CIVIL JURISDICTION WRIT PETITION (L.) NO. 91 OF 2019 Century Rayon Employees Consumers Co-operative Society Ltd., And Another ... Petitioners.
V/s.
State of Maharashtra And Others ... Respondents.
--- Mr. P. K. Dhakephalkar, Senior Advocate, a/with S/Shri Shardul Singh, Samit Shukla, Ms. Saloni Shah, Ms. Raveena Dhawan i/by DSK Legal for the Petitioners.
Mr. H. S. Venegaonkar, Additional G. P. for the State - Respondent Nos. 1 and 2.
Mr. Ramesh N. Dalal, Awal Karkun, Sub-Divisional Office, Kalyan, is present.
Mr. Arjun Gangaram Ingole, Gramvikas Officer, Grampanchayat, Kamba, Respondent No.3, is present. --- CORAM : R.M. BORDE & V.L. ACHLIYA,JJ.
DATE : FEBRUARY 04, 2019.
PC :
The grievance of the Petitioners in this petition is as regards failure on the part of the Respondents to determine the amount of compensation for utilizing their land for construction of a road and non-payment of the amount. The facts giving rise to the present petition are not disputed. Borey 1/2
spb/ 30wp091-19-2.odt The learned Additional Government Pleader appearing on behalf of the Respondent Nos. 1 and 2, on instructions, makes a statement that the amount of compensation receivable by the Petitioners towards the utilization of their land for construction of the road by the Respondents, would be determined by private negotiation and would be paid to the petitioners within a period of five months from today. Statement accepted.
In view of the statement made, as above, by the learned Additional G.P., the writ petition is disposed of. (V.L.ACHLIYA,J.) (R.M. BORDE) .....
[Note : This order is corrected as per speaking to the minutes order dated 22.02.2019 and uploaded] .....
Borey 2/2